65' EXPRESS SPORTFISH CONSTRUCTION
Page 2


December 3, 2007 December 17, 2007


Setting up the deck mold


Fitting first layer of topside core

December 26, 2007

January 2, 2008


Fitting second layer of topside core


Fitting core to stem

January 2, 2008 January 21, 2008

Deck mold set-up is all complete

Laying resin feed lines in preparation
for hull infusion

January 24, 2008

January 28, 2008


Start of infusion

End of infusion

January 28, 2008

 


Pulling bag and feed lines from hull

Pulling bag and feed lines from hull

February 4, 2008

February 25, 2008


Provisioning for hatches and lockers on deck mold

Fitting core for longitudinals
 